Anger at ‘appalling’ consultation over 14-month road closure for bridge work

A Fife MP has slammed Network Rail for its “appalling” engagement with a town as it prepares to shut the main street for 14 months to replace a rail bridge.

Richard Baker, MP for Glenrothes and Mid Fife, also wants the major Thornton project delayed until all contingency plans have been explored.

Network Rail is set to close the town’s Main Street for 14 months to work on replacing the rail bridge as part of the electrification of the Fife line. It will shut Main Street from May 12 and it will not re-open until July 2027 - and an “all vehicle” diversion will send traffic to the A92 for 62 weeks.

But that disruption and lack of engagement with residents and businesses has sparked a furious response from Mr Baker.

Richard Bake MP at the Glenrothes with Thornton station where the bridge works will result in a 14-month road closure (Pic: submitted)placeholder image
Richard Bake MP at the Glenrothes with Thornton station where the bridge works will result in a 14-month road closure (Pic: submitted)

The Labour MP has written to Network Rail to press for an explanation and to urge the rail authority to properly consult residents and businesses before proceeding.

He hit out: “The way this bridge closure has been communicated has been appalling. There was nothing official from Network Rail in recent months - it’s all been through the grapevine in recent days until now. Then we learn the project is meant to start next month.

“That would be bad enough if the bridge was to close for a fortnight but this is a 14 month project. To say I’m disappointed by the lack of community engagement from Network Rail is a huge understatement. It’s a breach of responsibility.

“That’s 62 weeks where people travelling by road could be forced to take lengthy detours, 62 weeks during which bus services to Kirkcaldy might be affected, 62 weeks where businesses could bear the absolute worst of it.” He said one local farmer who has land spanning both sides of the bridge and his business got in touch to say he depends on being able to use that route multiple times a day.

An impression of how the replacement bridge will look (Pic: Network Rail)placeholder image
An impression of how the replacement bridge will look (Pic: Network Rail)

“The effect on him and businesses like his could be enormous, and it’s no surprise he’s panicking,” said Mr Baker who has now written to Network Rail to press for an explanation and to urge the rail authority to properly consult residents and businesses before proceeding with electrification works.

He said: “Given the severity of this project’s impact on the local community, both in terms of the disruption and length of time it will take to complete, it’s incumbent on Network Rail to properly explore all alternative approaches first in consultation with people expected to bear the brunt of it.

“It’s also vitally important Network Rail discusses contingency plans with businesses whose livelihoods could be seriously affected. Until these processes are properly explored, works should absolutely be delayed.

It is the second major closure for work to be done on the massive electrification project. Bennochy Road in Kirkcaldy, one of the routes into town, will close for 12 months for the bridge to be demolished and rebuilt.

The work is required to ensure the structures meet the required height clearance for an electrified railway and allows the installation of the new overhead line equipment underneath.

Network Rail has organised two drop-in sessions for residents and businesses to find out more. They are Thornton Public Hall, on April 9 and 22, from 3:00pm until 6:30pm

In its letter, the company said: “Once work starts, the initial phase will involve several months of diverting a number of utilities from the existing bridge to safely house them on the temporary services bridge.

“Access to and from the station car park will remain. During the works pedestrians will still be able to access the station and cross where the bridge currently is via a temporary structure. The existing bridge will be demolished during a period of continuous working later in the year. The new bridge will be a pre-cast concrete structure and will be lifted into place in sections by crane.

“While we will carry out as much of the work as possible during the daytime, many of our activities can only take place at night when no trains are running, as this offers the safest environment for our team on site. This means there will be periods of overnight and weekend working. While we will do what we can to minimise this where possible, there will be some disturbance at times. We appreciate this isn’t ideal and thank you for your understanding.”