Motorists warned of overnight works on A92 in Glenrothes for nine weeks
Drainage improvements are to be carried out on the A92 at Bankhead Roundabout for the next nine weeks.
Amey will be carrying out the works on the Bankhead Roundabout in Glenrothes overnight from Monday, June 29 to Friday, August 28.


The £350,000 project, which Amey is undertaking on behalf of Transport Scotland, will improve drainage and safety in the area.
The works will take place on the A92, approximately 800 metres on either side of the roundabout.
The essential maintenance will be carried out under overnight week day lane restrictions between 7.30pm and 6.30am to ensure the safety of roadworkers and motorists.
While the work is being completed, single lane restrictions will be in place on the A92 in both directions to and from Kirkcaldy; on the A92 in both directions to and from Preston Roundabout; and on the Bankhead Roundabout itself.
There will also be a single lane restriction on Kinglassie Road on approach to the roundabout. The left filter lanes will be closed on the B921 and Woodside Way approaches. There will be no restrictions on James Watt Avenue or Beaufort Drive.
Amey say the works will improve safety and increase the efficiency of the filter drains for more than 32,000 road users who use the route each day.
Works are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.
Real time journey information can be obtained at www.trafficscotland.org