£250,000 roadworks plan for Levenmouth

Motorists can expect some disruptionMotorists can expect some disruption
Motorists can expect some disruption
Fife Council will be carrying out carriageway resurfacing on the A915 Standing Stane Road from May 22 to June 9 as part of a £250,000 road improvement plan for Levenmouth.

The work will be carried out in three phases:

Phase 1 Windygates roundabout with junction closure on A916 into Windygates. Traffic management three-way temporary traffic signals. Diversion route via Milton Road/A911.

Phase 2 Cameron roundabout with junction closure on B932 to Methilhill. Traffic management three-way temporary traffic signals. Diversion route via Percival Road (B930) and Methilhaven Road (A955).

Phase 3 A915 under temporary traffic signals and convoy.

Hide Ad
Hide Ad

Bus services will be affected and services 41, 41A, 44 and 49 will be re-directed. For more information contact Stagecoach on (01592) 645680 or visit www.stagecoachbus.com.

Access will be maintained for emergency services during the works.

David Brown, service manager said: “We maintain over 2,400 km of roads in Fife and we’re investing nearly £10 million this year repairing and improving them.

“We apologise for any inconvenience and delay caused by these essential works, and we’ll try to keep any disturbance to a minimum. Your patience and co-operation during this time is greatly appreciated.”

Breedon Aggregates Ltd will carry out the work.

For further information contact William O’Connor on 03451 55 55 55 ext: 444634.